Cottage to dock stairs
Summary
The client needs a system of stairs and landings to connect a waterfront cottage to a wooden pier approximately 19 feet below in elevation. The run is not a strait line, so a turn will be introduced to align the two. The styling is in keeping with the existing pier and is simple framework with minimal railings and posts. Finished materials are composite on top of pressure treated lumber.
Phase 1: layout & sitework
Because the stairs are to be built above a steeply sloped grade and include one if not two landings and must connect to the existing structure of the cottage, I decided to approach to the layout with the aid of quickly made plywood templates. The width on the plywood rips equals that of the actual framing lumber we will be using, so I am essentially creating a full size model. This allows us to work through the layout and various possibilities in real time. I started with a CAD drawing to set the general parameters and get the overall rise and run, but expect to make slight changes based on the real conditions.
Not a bad place to start the day and the project!
The main stair stringer (carriage) is laid out from 3 pieces of 8 foot rips. String is used to sight the assembly for straightness.
24 feet was easier to assemble on the ground. Butt straps were added at the joints and 1x3 stiffeners (2@16' stagger off the center to leave 2 feet free on each end for trimming the 24' span to final length) were added at the bottom edge to keep it straight. Side note, this may be the longest plywood thing I've made to date. Definitely awkward.
To keep all of the templates square to the house (and each others), I made some 3,4,5 triangles out of plywood and pine (for joining with staples).
Time to get rippin'
3,4,5 triangle assembly line.
Puting the templates in place was a top down process. I started by establishing the elevation for the first landing based on the existing grade at the patio. I used some pine strapping to carry the plane of the existing deck down to the grade and a 3,4,5 triangle to square up the landing 2x6 template. I ran this long, as the location of the top of the main carriage was TBD.
I started in on the main carriage by seeing where 24' of length would land on the sloped hill and checked the angle. Our rise and run has an angle of 34.5 degrees (off the horizontal) and the carriage was close as it lay on the slope. After I removed a spruce tree that was (unfortunately) exactly where the carriage needed to be and excavated a little bit, the carriage was sitting at exactly the right angle. I attached it to the upper landing 2x6 template in a location that would allow the landing to terminate on top of the preexisting piers with a 4x4 post. So, the “plumb” cut (complimentary of 34.5 so 55.5 ) of the carriage would land in this location. I marked all of this on the two templates and screwed them together. A couple more 3,4,5 triangles helped to keep things square.
The elevation of the lower landing was a bit tricky. The lower landing angles slightly off the upper landing and stair assembly in order to align with the existing structure below. This means I needed to intersect a line parallel with the pier, at the elevation of the lower landing, to a point on the carriage so that the angle change would happen where the outside edges of the sloped carriage and the flat landing would meet. Otherwise, the landing would be off center. If the landing was too high, it would be off to one side. Too low, and the landing would be off to the other side. Once this intersection was found (with the previously mentioned templates and string lines from the pier), I was able to decide where to put the landing so it's elevation would intersect the main carriage.
The final run of stairs from the lower landing down to the pier was kind of easy, except that I had to make sure that the final step would land approximately 48” from the start of the pier. I used simple calculation of the total run needed for the steps and worked backwards to figure out where the landing needed to end to make this happen.
The footings for the main carriage, lower landing, and lower carriage could now be located and dug. The large footing is placed at the base of the main carriage directly under where it mounts to the landing. The smaller footings are located directly under the end of the landing before the final stairs. Digging was extremely hard as the topsoil is littered with all the roots that can penetrate the next 18 inches of chossy rock and gravel. I was able to make it to island bedrock at around 32”. Main footer is 2 12” sono tubes with #4 rebar driven 12” into bedrock with a 4” thick 24” x 60” pad on top with #4 reinforcement. The small footings are 12” sono tubes with #4 rebar driven into bedrock as well.




All the template work and string lines allowed me to actually figure out an intersection point for the base of the main carriage and the lower landing. Here are the footings.

The Pier in all it's September afternoon glory. Not a bad spot to bang nails. Which I haven't done much of yet.
View from dock to cottage showing the complete run, top to bottom.
16 bags of concrete escorted down the hill by a ramp and gravity.
Use an ancient hammer drill to tap into bedrock.
12” inches deep.
Footings and rebar reinforced pad for the main stair base.
Have a helper and strip the forms the day after.
Phase 2
TBD